A 360 ton crane belonging to Imperial Crane of Chicago was just beginning a routine lift of an air conditioning unit onto a roof, in downtown Chicago on Saturday, when the outriggers on one side crashed through the tarmac. The Crane was rigged with a long jib but the main boom was retracted,
As the crane tipped backwards the boom, which was at its at full elevation -maximum angle, crashed into building behind, number 17 Wabash, causing extensive damage to the upper floors.
Please register to see all images
Imperial Cranes stranded 360 toner on Saturday
The crane was working in a narrow street in ‘Jewelers Row’ and as is now clear, was working over a basement. No one was hurt in the accident.
Imperial immediately sent in another crane to rescue the first, but not only was it not up to the job, but a web sling being used to lift the crane snapped during the attempt.
A larger crane was called in which did manage to shift the stricken crane a little, but it too proved insufficient for the task. As we go to press a third and yet larger crane was attempting to extract the fallen crane from the hole.
Imperial Crane said that the City, which issued a permit allowing the road to be closed and the lift to go ahead, did not mention that the street was built over a void. Vice president Wes Austin is quoted in the local press as saying "Nobody told us the alley was vaulted, It is always a scary thing for a crane company.''
A spokesman for the city Office of Emergency Management and Communications, would confirm only that the company had the proper permit. Although a city employee on site is quoted as saying: “It was obvious from grills on the street that the roadway was vaulted underneath, it's up to a crane operator to determine if a crane is too heavy for the street”.
Not only has the street remained closed but several train lines were diverted to avoid the area.
Comments